Arte SheetsLearn. Try. Understand.

Aerospace MIL-A-8625 Aluminum Anodizing, Type III Hardcoat & CNC Pre-Plate Allowance

Aluminum Sulfuric Anodizing "720 Rule" & Growth Formula

Calculate Target Coating Thickness in Mils (0.001 in), Sulfuric-Bath Anodizing Tank Time via the 720 Rule (min), Total Titanium-Rack DC Rectifier Load (A), and Outside-Diameter Dimensional Growth (um).

Anodizing converts aluminum INTO Al2O3—50% penetrates inward and 50% grows outward, shrinking bores and swelling ODs by 1x total coating thickness

Unlike electroplating (which deposits 100% of metal ON TOP of the part surface), MIL-A-8625 Type II decorative and Type III hardcoat sulfuric-acid anodizing electrochemically oxidizes the aluminum substrate itself into porous hexagonal Al2O3. Because Al2O3 occupies roughly twice the molar volume of consumed metallic Al, ~50% of Total Coating Thickness t_ox (um) penetrates INWARD into the parent metal while ~50% builds OUTWARD per surface—meaning an external shaft OD grows by 2 * (0.50 * t_ox) = +1.0 * t_ox (and a precision bearing bore SHRINKS by -1.0 * t_ox), forcing CNC machinists to pre-machine bores oversize and shafts undersize before hardcoating. Across aerospace finishing lines, tank cycle time follows the classic 720 Amp-Minute Rule: 720 amp-minutes per square foot (ASF * min) grows 1.0 mil (25.4 um) of anodic oxide, so Time_min = (K_720 * (t_ox_um / 25.4)) / Current_Density_ASF.

Verify on a MIL-A-8625 Type III Hardcoat Aluminum Load—Target_Total_Oxide_Thickness t_ox = 50.0 um (1.969 mils in E2, B2), Refrigerated_Bath_Current_Density = 24.0 ASF (2.58 A/dm², B3), Wetted_Titanium_Rack_Area = 14.5 ft² (B4), and Anodizing_Constant K_720 = 720.0 ASF·min/mil (B5): Required Bath Cycle Time equals 59.06 minutes (E3), Total DC Rectifier Load equals 348.0 A (E4), and Shaft/Bore Diameter Shift (2 * 50% build) equals 50.0 um (0.050 mm!, E5).

MIL-A-8625 Anodizing KPI (50 um Type III @ 24 ASF on 14.5 ft², K=720)FormulaVerified Output
Target Oxide Thickness (mils)Target_Oxide_um / 25.41.969 mils (0.709 mils @ 18 um Type II)
720-Rule Tank Time (min)(K_720 * (Target_um / 25.4)) / ASF59.06 min (34.02 min @ 18 um, 15 ASF)
Total Rack Rectifier Current (A)Current_Density_ASF * Rack_Area_ft2348.0 A (217.5 A @ 15 ASF Type II)
Shaft OD Growth / Bore Shrink (um)2 * (0.50 * Target_Oxide_um)50.0 um (18.0 um @ 18 um Type II)

MIL-A-8625 Sulfuric Anodizing 720-Rule Cycle Time & Diameter Shift Formula

Validate Target_Oxide in (1, 125] um, Current_Density in [8, 48] ASF (12–18 ASF ambient Type II; 24–36 ASF chilled 0 °C Type III hardcoat), Rack_Area > 0 ft², and Rule_Constant in [650, 820] ASF·min/mil (720 standard 6061-T6; ~760–780 high-copper 2024-T3 where acid dissolution lowers net efficiency).

=LET(tx_u, B2, cd_a, B3, ar_f, B4, kr_c, B5, IF(OR(tx_u <= 1, tx_u > 125, cd_a < 8, cd_a > 48, ar_f <= 0, kr_c < 650, kr_c > 820), "Invalid Anodize Input", ROUND(2 * (0.5 * tx_u), 1)))

Clear Type II Decorative Anodize Schedule Check (Set Oxide = 18.0 um & Current Density = 15.0 ASF)

Switch to an 18.0 um (0.709 mil, E2) MIL-A-8625 Type II clear coat at 15.0 ASF (B2 = 18, B3 = 15): Bath Cycle Time E3 drops to 34.02 min, Rectifier Load E4 eases to 217.5 A, and Bore Shrinkage / OD Growth E5 drops to 18.0 um.

=IF(ISTEXT(E5), E5, ROUND((B5 * (B2 / 25.4)) / B3, 2))

Try the example

Use the original values or change them to test your understanding.