Chvorinov Sand-Casting Modulus & Riser Sizing Formula

Calculate Casting Cooling Modulus M_c = V/A (cm), Chvorinov Solidification Time t_s = B*(V/A)^n (min), Minimum Blind Cylindrical Riser Diameter D_r = H_r (cm), and Riser Feed Volume (cm³).

If a sand-casting riser freezes BEFORE the heavy boss it feeds, shrinkage cavities form straight inside the casting

Molten gray iron, steel, and aluminum alloys shrink 3%–7% volumetrically upon freezing. Nicolas Chvorinov proved via transient 1D mold heat-conduction theory that a casting of volume V_c (cm³) and heat-dissipating mold surface area A_c (cm²) solidifies in time t_s = B * ((V_c / A_c)^n) minutes—governed by its Geometric Cooling Modulus M_c = V_c / A_c (cm), Mold Constant B (min/cm², typically ~1.8–2.4 in insulating silica green sand vs ~0.6–0.9 against iron chills), and exponent n ~= 2.0. To guarantee Directional Solidification where liquid feed metal flows continuously into the shrinking casting until the very last core freezes, foundry engineers size a sacrificial Riser to stay molten ~44% longer by setting Riser Modulus M_r = k_safe * M_c (k_safe = 1.20 -> 1.20^2 = 1.44x freeze time). For a sand-enclosed blind cylindrical riser of optimal height H_r = D_r, modulus M_r = (PI()*D_r^3/4) / (1.5*PI()*D_r^2) = D_r / 6 yields Minimum Riser Diameter D_r = 6 * M_r cm.

Try this 3,600 cm³ Ductile-Iron Valve Body Sand Casting first—Casting_Volume V_c = 3,600.0 cm³ (B2), Cooling_Surface_Area A_c = 1,500.0 cm² (B3 -> Casting Modulus M_c = 2.40 cm in E2), Green_Sand_Mold_Constant B = 2.10 min/cm² (B4), Chvorinov_Exponent n = 2.00 (B5), and Riser_Modulus_Factor k_safe = 1.20 (B6): Casting Solidification Time hits 2.10 * (2.40^2) = 12.10 minutes (E3), Required H=D Blind Riser Diameter equals 6 * (1.20 * 2.40) = 17.28 cm (E4), and Cylindrical Riser Volume equals 4,052.5 cm³ (E5). In a shared Arte Sheets foundry gating workbook, a suggester can test inserting cast-iron chills (B = 0.85 min/cm²) in Suggest Mode while asking a hint-first AI prompt ("Why does adding an exothermic sleeve cut required riser volume in half without violating Chvorinov’s directional freeze rule?") before the owner releases the pattern.

Chvorinov Foundry KPI (Vc=3,600 cm³, Ac=1,500 cm², B=2.10 min/cm², n=2.0, k=1.20)FormulaVerified Output
Casting Cooling Modulus Mc (cm)Casting_Volume_cm3 / Surface_Area_cm22.40 cm
Casting Solidification Time (min)Mold_Const_B * (Modulus_Mc ^ Exp_n)12.10 min (4.90 min @ B=0.85 chill)
Min Blind Riser Diameter Dr=Hr (cm)6 * (Safety_k * Modulus_Mc)17.28 cm
Cylindrical Riser Volume (cm³)(PI() / 4) * (Riser_Diam_Dr ^ 3)4,052.5 cm³

Chvorinov Cooling Modulus & H=D Cylindrical Riser Sizing Formula

Validate Casting_Volume > 0, Surface_Area > 0, Mold_Constant B > 0, Chvorinov_Exponent n in [1.5, 2.5], and Riser_Modulus_Safety_Factor k_safe >= 1.05.

=LET(vc_c, B2, ac_s, B3, bm_c, B4, ex_n, B5, ks_f, B6, IF(OR(vc_c <= 0, ac_s <= 0, bm_c <= 0, ex_n < 1.5, ex_n > 2.5, ks_f < 1.05), "Invalid Foundry Input", LET(mc_m, vc_c / ac_s, dr_c, 6 * ks_f * mc_m, ROUND((PI() / 4) * (dr_c ^ 3), 1))))

Metal Chill Rapid Directional Freeze Check (Set Mold Constant B = 0.85 min/cm²)

Place external cast-iron chills against the heavy boss (lowering effective Mold_Constant B4 from 2.10 to 0.85 min/cm²): Local Boss Solidification Time E3 drops from 12.10 minutes down to 4.90 minutes—eliminating isolated hot-spot shrinkage porosity.

=IF(ISTEXT(E5), E5, ROUND(B4 * ((B2 / B3) ^ B5), 2))

Try the example

Use the original values or change them to test your understanding.