Arte SheetsLearn. Try. Understand.

Hollow Polymer Processing, Rotational Molding Powder Shot Weight & Cavity Tumbling Fill

Rotational Molding Powder Shot Weight & Bulk Fill Formula

Calculate Required Pulverized PE Charge Weight (kg), Unmelted Powder Loose Volume (L), Cold-Mold Volumetric Fill Fraction (%), and Solid-to-Powder Compaction Ratio.

Pulverized rotomolding polyethylene takes up 2.56x MORE volume than solid plastic—overfilling a hollow mold past 55% chokes powder tumbling

Biaxial Rotational Molding (Rotomolding) tumbles 35-mesh pulverized LLDPE powder (Apparent Bulk Density rhobulk ≈ 340–400 kg/m³ per ASTM D1895) inside a zero-pressure cast-aluminum or sheet-steel shell of Internal Surface Area Amold (m²) and Enclosed Cavity Volume Vmold (L) inside a 280 °C convection oven until Peak Internal Air Temperature (PIAT ≈ 200 °C) sinters a stress-free hollow tank or kayak of Target Wall Thickness t (mm) and Solid Polymer Density rhosolid (~934–940 kg/m³). Charge Weigh-Out follows **Mshot = Amold * (t / 1,000) * rhosolid (kg), occupying Cold Loose Powder Volume Vloose = (Mshot / rhobulk) * 1,000 (L). Crucially, Cold Cavity Powder Fill Fill% = (Vloose / Vmold) * 100% MUST stay below ~55%–60%** so the powder pool cascades freely across every internal rib instead of locking solid (requiring split two-drop "drop-box" charging when Fill% > 60%).

Verify on a 420-Liter Agricultural Sprayer Tank Mold—Internal_Surface_Area Amold = 3.85 m² (B2), Enclosed_Cavity_Volume Vmold = 420.0 L (B3), Target_Wall_Gauge t = 5.20 mm (B4), Solid_LLDPE_Density rhosolid = 936 kg/m³ (B5), and 35-Mesh_Powder_Bulk_Density rhobulk = 365 kg/m³ (B6): Required Powder Shot Weight equals 18.74 kg (E2), Cold Loose Volume equals 51.3 L (E3), Cold Mold Fill sits comfortably at 12.22% (E4), and Solid-to-Bulk Compaction Ratio equals 2.56 (E5).

ARM Rotomolding Charge KPI (A=3.85 m², PE 936/365 kg/m³: 420L/5.2mm vs Flat 110L/8.5mm)FormulaVerified Output
Powder Charge Shot Weight (kg)Surface_Area_m2 * (Wall_mm / 1000) * rho_solid18.74 kg (30.63 kg @ heavy 8.5 mm wall)
Cold Loose Powder Volume (L)(Shot_Weight_kg / Powder_Bulk_Density) * 100051.3 L (83.9 L loose powder)
Cold Mold Cavity Fill (%)(Loose_Powder_Vol_L / Mold_Vol_L) * 10012.22% (76.29% > 60% CHOKED @ 110 L)
Solid-to-Bulk Density RatioSolid_PE_Density / Powder_Bulk_Density2.56 : 1

Rotomolding Shell Mass Balance & Cold-Powder Free-Cascade Fill Formula

Validate Mold_Area A > 0.05 m², Mold_Volume V > 1 L, Wall_Gauge t in [1.0, 25.0] mm, Solid_Density in [850, 1,500] kg/m³, and 0.25 * rhosolid <= rhobulk <= 0.65 * rhosolid.

=LET(am_s, B2, vm_l, B3, tw_m, B4, rs_k, B5, rb_k, B6, IF(OR(am_s <= 0.05, vm_l <= 1, tw_m < 1, tw_m > 25, rs_k < 850, rs_k > 1500, rb_k < 0.25 * rs_k, rb_k > 0.65 * rs_k), "Invalid Rotomold Input", ROUND(rs_k / rb_k, 2)))

Narrow Double-Wall Dock Float (V = 110 L, Wall = 8.5 mm) Drop-Box Choking Check

Mold a flat, high-surface-area 110 L marine float with heavy 8.5 mm armor walls (B3 = 110, B4 = 8.5): Shot Weight E2 rises to 30.63 kg (83.9 L loose powder in E3), driving Cold Cavity Fill E4 to 76.29%—starving corner tumbling unless 40% of the resin is held inside an insulated pneumatic drop-box and released mid-oven cycle.

=IF(ISTEXT(E5), E5, LET(ms_k, B2 * (B4 / 1000) * B5, vl_l, (ms_k / B6) * 1000, ROUND((vl_l / B3) * 100, 2)))

Try the example

Use the original values or change them to test your understanding.

Further reading